  3. Peti dam: 4,052 cracks tracked from one campaign to the next since 2022
Cemig · São Gonçalo do Rio Abaixo, Minas Gerais, Brazil · 2022–2025

Peti dam: 4,052 cracks tracked from one campaign to the next since 2022

Four annual campaigns on an arch dam in Minas Gerais: a baseline of 4,052 cracks surveyed at 0.8 mm per pixel in 2022, then only what appears, lengthens or becomes more visible.

Peti dam: 4,052 cracks tracked from one campaign to the next since 2022
São Gonçalo do Rio Abaixo, Minas Gerais, Brazil
4 052cracks at baseline, 2,023 m in total
0,8 mmper pixel on the downstream face
4campaigns: 2022, 2023, 2024, 2025
68comparison cells on the downstream face
6new or longer cracks in 2025

Background

Built in 1944-1945 on the Santa Bárbara river, about a hundred kilometres from Belo Horizonte, the Peti arch dam feeds a 9.4 MW plant operated by Cemig. Its concrete is affected by alkali-aggregate expansive reactions; following an external study in 2019, the operator added drone inspection of the upstream and downstream faces and the crest to the dam’s safety plan. It needed a complete baseline of the downstream face, then campaigns that could be strictly compared from one year to the next.

What we did

In September 2022, a multirotor RTK drone with a 45-megapixel full-frame sensor flew a general survey of 932 photos, then a 3D flight plan of 1,400 photos 6.5 m from the downstream face, computed on the model: 0.8 mm per pixel. The photos were reprojected onto three face orthophotos, one cylindrical for the arch and two planar for the side blocks, on which 4,052 cracks were drawn and classified into three families by opening and length, 2,023 m in total. At each following campaign the GNSS base goes back on the same concrete benchmark on the left bank, the face orthophotos are produced on identical projections and registered on control points of the face, and only two categories are drawn: new or longer cracks, and cracks or sections that have become more visible. A compact RTK drone, flown manually, covers the upstream face and hard-to-reach areas. This picked up 22 new or longer cracks in 2023, 4 in 2024 and 6 in 2025; the 2025 report concludes that the downstream face has remained stable since monitoring began.

3 related missions in the log

  1. InspectionBrazil

    Fourth campaign on the Peti dam

    Peti, São Gonçalo do Rio Abaixo, Minas Gerais · Cemig

    From 22 to 24 September 2025: 2,037 photos in 21 flights and 12.7 km flown, 7 orthophotos totalling 3.9 gigapixels, 71 plates including 68 comparison plates; six new or longer cracks since 2024, downstream-face stability confirmed since the 2022 baseline.

    • 2 037 photos
    • 6 new cracks
    Read the article
  2. InspectionBrazil

    Third campaign on the Peti dam

    Peti, São Gonçalo do Rio Abaixo, Minas Gerais · Cemig

    From 26 to 28 August 2024: 1,610 photos of the downstream face and 832 of the upstream face from 5 m away, 2023 and 2024 campaigns registered on the 2022 reference; four new cracks, cumulative length almost unchanged.

    • 4 new cracks
    Read the article
  3. InspectionBrazil

    Second annual campaign on the Peti dam

    Peti, São Gonçalo do Rio Abaixo, Minas Gerais · Cemig

    From 12 to 15 September 2023: 1,649 photos of the faces from 6.5 m away, face orthophotos registered on the 2022 baseline (4,052 cracks); 22 new or longer cracks and 54 more visible ones recorded.

    • 22 new cracks
    • 0,8 mm per pixel
    Read the article

All missions

Gallery

Tell us about your project

Location, area or structure, expected deliverables and timing: with these details we can propose a method and a quote.

French Guiana3 rue Gramme
97310 Kourou
French Guiana
MartiniqueDomaine de Château Gaillard
Route des Trois-Îlets
97229 Les Trois-Îlets
Martinique
BrazilRua Santa Luzia, Centro
20030-041 Rio de Janeiro – RJ
Brazil