From dams in Brazil to the launch complexes of Kourou, a selection of our work with its figures. Each project has its own page: the background, method, deliverables and images.

257missions in the log since 2023
30+launch campaigns in Kourou
12 647hectares of orthophotos for EPFA Guyane
2 492anomalies mapped on a plant in Bahia
The Ariane 6 launch complex under construction

All projects

53 detailed projects. Filter by service or territory.

The Ariane 6 launch complex construction, filmed and photographed from 2018 to 2021
Guiana Space Centre, Kourou2018–2021

The Ariane 6 launch complex construction, filmed and photographed from 2018 to 2021

From 2018 to 2021, aerial photo and video campaigns on the ELA4 construction site: fourteen films published by the Guiana Space Centre, photos used by ESA, Espace & Exploration and Latitude 5.

14 films published by the Guiana Space Centre
Space centreConstruction monitoring
Hydroelectric plant on the São Francisco river: 2,492 anomalies mapped in three days on site
São Francisco river, Bahia, Brazil2025

Hydroelectric plant on the São Francisco river: 2,492 anomalies mapped in three days on site

Baseline survey of a hydroelectric plant on the São Francisco river, in the state of Bahia: 11,809 photos in 33 flights, 9 orthophotos totalling 46 gigapixels, two 3D models, a virtual tour and a web interface for the operator’s engineers.

11 809 photos in 33 flights
Structural inspection
Juquiá complex: seven dams with crests of 140 to 265 m
Energy producerJuquiá river basin, São Paulo State, Brazil2026–2027

Juquiá complex: seven dams with crests of 140 to 265 m

Two-year contract signed in July 2026 with an energy producer: the seven dams flown over in August, the faces of Salto do Iporanga and then Serraria surveyed in detail, the rest scheduled for the 2027 dry season.

7 dams
Structural inspectionSurveying and LiDAR
Eleven solar plants in 2026: 33,333 panels checked one by one
GenergiesMartinique, Guadeloupe and French Guiana2026

Eleven solar plants in 2026: 33,333 panels checked one by one

June to September 2026: eleven plants surveyed by thermography for Genergies in Martinique, Guadeloupe and French Guiana: 33,333 panels checked one by one.

33 333 panels checked in 2026
Thermography
Launch campaigns: fifteen launches covered in Kourou from 2017 to 2019
Guiana Space Centre, Kourou2017–2019

Launch campaigns: fifteen launches covered in Kourou from 2017 to 2019

Aerial photography of the launch complexes during Ariane 5, Soyuz and Vega campaigns, within the windows authorised by the base: fifteen launches from December 2017 to December 2019.

15 launches covered from 2017 to 2019
Space centreFilm, photo and 360°
Flame trenches of the Ariane 6 launch complex: inspections and a digital twin at 1.5 mm per pixel
CNES, then Groupe ADFAriane 6 launch complex, Guiana Space Centre2023–2025

Flame trenches of the Ariane 6 launch complex: inspections and a digital twin at 1.5 mm per pixel

Since November 2023 we have photographed the inside of the two flame trenches of the ELA4, which carry the engine exhaust away at lift-off. In 2025 a photogrammetric survey turned them into a digital twin and eight orthophotos at about 1.5 mm per pixel.

2 flame trenches, east and west of the pad
Space centreStructural inspectionSurveying and LiDAR
Jet guide and deflector of the ELA4: inspected after the first four Ariane 6 launches
CNES, then Groupe ADFAriane 6 launch complex, Guiana Space Centre2024–2025

Jet guide and deflector of the ELA4: inspected after the first four Ariane 6 launches

After the maiden flight of Ariane 6 in July 2024, then after the launches of March, August and November 2025, we photographed the jet guide of the ELA4, outside and inside over its full height, together with its deflector.

4 Ariane 6 launches followed by an inspection
Space centreStructural inspection
Sounding rocket launch complex: 680 hectares of photogrammetry for a wind study
CNESSounding rocket launch complex, Guiana Space Centre2021–2026

Sounding rocket launch complex: 680 hectares of photogrammetry for a wind study

On 15 and 16 April 2026, for CNES, oblique imaging flights covered 6.77 km² around the sounding rocket launch complex: 25,928 images, a 667-million-point cloud and a 3D mesh for a wind simulation.

680 ha surveyed in two days of flights
Space centreSurveying and LiDAR
ELA4 hydrogen burn pond: the igniters checked with a thermal camera, test after test
CNES, then Eiffage Énergie SystèmesAriane 6 launch complex, Guiana Space Centre2023–2026

ELA4 hydrogen burn pond: the igniters checked with a thermal camera, test after test

From June 2023 to April 2026 we checked the igniters of the ELA4 hydrogen burn pond with a thermal camera: first for CNES during the Ariane 6 tests, then for Eiffage Énergie Systèmes at every launch preparation.

16 visits from June 2023 to April 2026
Space centreThermography
Peti dam: 4,052 cracks tracked from one campaign to the next since 2022
CemigSão Gonçalo do Rio Abaixo, Minas Gerais, Brazil2022–2025

Peti dam: 4,052 cracks tracked from one campaign to the next since 2022

Four annual campaigns on an arch dam in Minas Gerais: a baseline of 4,052 cracks surveyed at 0.8 mm per pixel in 2022, then only what appears, lengthens or becomes more visible.

4 052 cracks at baseline, 2,023 m in total
Structural inspection
12,647 hectares of orthophotos at 3.5 cm for EPFA Guyane
EPFA GuyaneCayenne, Matoury, Rémire-Montjoly, Macouria, Kourou and Cacao, French Guiana2023–2026

12,647 hectares of orthophotos at 3.5 cm for EPFA Guyane

From 4 December 2023 to 1 March 2024, eight sectors photographed at 3.5 cm per pixel, from Cayenne to Cacao: 343 flights, 184,464 photos, 50 ground control points and 26 check points. A second 6,545-hectare campaign began on 16 October 2026; its first sector was delivered on 19 October.

12 647 hectares in eight sectors
Surveying and LiDAR
Corossony solar plant: 1,472 concrete footings surveyed at 2 mm per pixel before repowering
AlbiomaRoute de Saint-Élie, Sinnamary2024–2025

Corossony solar plant: 1,472 concrete footings surveyed at 2 mm per pixel before repowering

A 1:500 topographic plan of the plant in operation in September 2024, then the position and height of each of the 1,472 footings kept for the new structures, in December 2025.

1 472 concrete footings surveyed
Surveying and LiDAR
Post-launch inspections of the Ariane 5, Soyuz and Vega zones
Groupe ADFGuiana Space Centre, Kourou2018–2026

Post-launch inspections of the Ariane 5, Soyuz and Vega zones

Since 2018, after launches, we have photographed the structures of the launch zones for their revalidation, as on the Soyuz launch zone on 4 January 2021.

2018 first post-launch inspections
Space centreStructural inspection
Martinique coastline: three precision surveys, from 1.78 to 3.72 cm
DEAL Martinique and BRGMSaint-Pierre, Le Vauclin, Le Prêcheur — Martinique2025–2026

Martinique coastline: three precision surveys, from 1.78 to 3.72 cm

At Pointe des Sables in Le Vauclin and in Saint-Pierre for DEAL Martinique, at the mouth of the Prêcheur river for BRGM during the lahar crisis: three orthophotos whose accuracy was measured on independent targets, delivered between one and five days after the flights.

1.78 cm planimetric accuracy in Saint-Pierre
Surveying and LiDAR
Jarry-Houëlbourg: 327 hectares of wetland in a 2.36 cm orthophoto
Conservatoire du littoralJarry-Houëlbourg, Baie-Mahault, Guadeloupe2026

Jarry-Houëlbourg: 327 hectares of wetland in a 2.36 cm orthophoto

For the Conservatoire du littoral, the orthophoto and surface model of the Jarry-Houëlbourg wetland and its edge with the business district: 15,445 images taken over one weekend in February 2026, 3.64 cm root-mean-square error on six check points.

327 hectares
Surveying and LiDAR
Salvation Islands: LiDAR and photogrammetry of the three islands
CNESSalvation Islands, off Kourou2023–2025

Salvation Islands: LiDAR and photogrammetry of the three islands

For CNES, which manages the site, LiDAR and photogrammetric surveys of Île Royale, Île Saint-Joseph and Devil’s Island, from 2023 to 2025.

3 islands surveyed
Space centreSurveying and LiDAR
Waste in western French Guiana: eight visits in Saint-Laurent, four Maroni villages at 1 cm
CCOGSaint-Laurent-du-Maroni, Apatou and the upper Maroni2024–2026

Waste in western French Guiana: eight visits in Saint-Laurent, four Maroni villages at 1 cm

Since October 2024, photos taken from the same viewpoints at every visit to the Saint-Laurent-du-Maroni waste storage facility, with a 3 cm orthophoto and a plan since December 2024; in February 2026, the waste sites of four river villages surveyed at 1 cm.

8 visits in Saint-Laurent
Surveying and LiDARConstruction monitoring
Roy canal: 7.7 km of LiDAR from a dugout canoe, in the Kaw marshes
DGTM GuyaneRoy canal, Kaw marshes, French Guiana2024

Roy canal: 7.7 km of LiDAR from a dugout canoe, in the Kaw marshes

In late June 2024, in the Kaw-Roura marshes nature reserve: a 7,700 m by 200 m corridor surveyed from the boat, 155 million points and the ground restored beneath the vegetation.

7,7 km of canal
Surveying and LiDAR
Virtual tour of the Ariane 6 launch complex: 200 360° panoramas
CNESGuiana Space Centre, Kourou2023

Virtual tour of the Ariane 6 launch complex: 200 360° panoramas

For CNES, a web-based virtual tour of the launch complex, to prepare Toulouse-based engineers before their mission in French Guiana and brief them on safety protocols.

200 360° panoramas
Space centreFilm, photo and 360°
63 and 90 kV lines: three pylons in the Guadeloupe rainforest, five wooden poles in French Guiana
OmexomBouillante – Sainte-Rose, Guadeloupe; Matiti, Macouria, French Guiana2026

63 and 90 kV lines: three pylons in the Guadeloupe rainforest, five wooden poles in French Guiana

For Omexom, in June and July 2026: three 63 kV pylons in the Guadeloupe national park, then in French Guiana a fault check after an outage and five wooden supports of a 90 kV line.

3 63 kV pylons in Guadeloupe
Structural inspection
Petit-Saut sawmill: 31 monthly visits, three time-lapses and eight years of missions on the lake
Triton GuyanePetit-Saut lake, Sinnamary, French Guiana2018–2026

Petit-Saut sawmill: 31 monthly visits, three time-lapses and eight years of missions on the lake

For Triton, which harvests the drowned timber of the Petit-Saut lake, we photographed the lake as early as 2018, then followed the sawmill construction every month from March 2023 to September 2025. In 2026 came a virtual tour, a corporate film and stockpile volumes on the platforms.

31 monthly visits, March 2023 – September 2025
Construction monitoringFilm, photo and 360°Surveying and LiDAR
Larivot bridge: the repair of a 1,225 m bridge, filmed over eight visits
FreyssinetLarivot bridge, Cayenne – Macouria2024–2026

Larivot bridge: the repair of a 1,225 m bridge, filmed over eight visits

Since October 2024, aerial and ground photos and videos at each phase of the repair works on the existing bridge, and in March 2026 a four-to-five-minute film for the contractor’s convention.

8 visits completed, October 2024 to July 2026
Construction monitoringFilm, photo and 360°
Saint-Jean-du-Maroni: 125 hectares of the relegation heritage by LiDAR
Préfecture de GuyaneSaint-Jean-du-Maroni, Saint-Laurent-du-Maroni2024

Saint-Jean-du-Maroni: 125 hectares of the relegation heritage by LiDAR

For the regional historic monuments service, a 25 cm terrain model beneath the vegetation of the former relegation camp, surveyed from 23 to 25 October 2024 to prepare the protection order.

125 contiguous hectares
Surveying and LiDAR
95 Space Centre buildings inspected in six days
Groupe ADFGuiana Space Centre, Kourou2020

95 Space Centre buildings inspected in six days

In early June 2020, for Groupe ADF, inspection of the façades, roofs and roads of 95 buildings on the base, anchor points and welds included, in six days.

95 buildings
Space centreStructural inspection
New LiDAR: two surveys of the Macouria solar plant site, with 1.95 and 2.97 cm vertical error
Corsica SoleMacouria, French Guiana2026

New LiDAR: two surveys of the Macouria solar plant site, with 1.95 and 2.97 cm vertical error

The fleet’s new LiDAR system, validated in June 2026 on our reference points, surveyed the site of Corsica Sole’s photovoltaic plant in Macouria twice in one month, to measure earthwork volumes.

487 points per m², first survey
Surveying and LiDAR
Grand-Case aerodrome: LiDAR and a 3 cm orthophoto beside an active runway
Edeis Aéroport Saint-Martin, with Tilaya DronesGrand-Case, Saint-Martin2026

Grand-Case aerodrome: LiDAR and a 3 cm orthophoto beside an active runway

In April 2026 we surveyed by LiDAR, for the aerodrome operator, a wooded area of about 8 hectares beside the runway, at no more than 30 m above ground and in coordination with the AFIS, then re-registered the existing airfield drawing in the current reference system.

30 m maximum height granted by the AFIS
Surveying and LiDAR
Saint-Élie: 625 hectares without a GNSS station within twenty kilometres
Municipality of Saint-ÉlieSaint-Élie, French Guiana2024

Saint-Élie: 625 hectares without a GNSS station within twenty kilometres

3.5 cm orthophoto of 625 hectares around an inland village, registered on a base and five control points measured by precise point positioning, with no reference station in range.

625 hectares
Surveying and LiDAR
Tests of the P120C motor for Ariane 6 and Vega C
Guiana Space Centre, Kourou2019–2020

Tests of the P120C motor for Ariane 6 and Vega C

Our aerial footage of the second bench test of the P120C, on 28 January 2019, was published by CNES; in July 2020 we photographed the transfer of the third motor to the test bench.

28 janvier 2019 second bench test, filmed by drone
Space centreFilm, photo and 360°
Furnas test blocks: cracks measured at 0.15 mm per pixel
FurnasAparecida de Goiânia, Goiás, Brazil2022–2023

Furnas test blocks: cracks measured at 0.15 mm per pixel

For Furnas’ research programme on concrete affected by expansive reactions, face-by-face measurement of the cracks of 80 cm test cubes: 26 blocks in 2022 at 0.25 mm per pixel, 14 blocks in 2023 at 0.15 mm.

0,15 mm per pixel in 2023
Structural inspection
Kourou lakes: three water bodies at 13 mm, then erosion monitoring of the Canal de l’Ouest
Communauté de communes des SavanesKourou, French Guiana2024–2026

Kourou lakes: three water bodies at 13 mm, then erosion monitoring of the Canal de l’Ouest

13 mm orthophotos of the Bois Chaudat, Bois Diable and Marie-Claire lakes in November 2024; since September 2026, erosion-monitoring campaigns on Bois Chaudat lake and the Canal de l’Ouest, flown at low tide.

13 mm per pixel in 2024
Surveying and LiDAR
BHNS works at Balata: two time-lapse cameras for fourteen months
Ribal TPRN2, from Balata to the PROGT roundabout, Matoury2024–2025

BHNS works at Balata: two time-lapse cameras for fourteen months

From 8 November 2024 to 31 December 2025, two time-lapse units and five days of aerial and ground filming on the RN2 upgrade in Matoury, for the civil works contractor.

14 months of time-lapse
Construction monitoringFilm, photo and 360°
More than 1,000 rooftops surveyed since 2019 for a solar installer
SystekoMartinique, French Guiana, Guadeloupe2019–2026

More than 1,000 rooftops surveyed since 2019 for a solar installer

Pre-installation roof surveys, 3D shading studies and thermal surveys of rooftop plants, across three territories since 2019.

1 000+ rooftops surveyed for panel layouts since 2020
Surveying and LiDARThermographyStructural inspection
Bellefontaine: 8,996 panels surveyed by thermography under medium-voltage lines
GenergiesBellefontaine, Martinique2026

Bellefontaine: 8,996 panels surveyed by thermography under medium-voltage lines

A 4.9 MWp ground-mounted plant beneath medium-voltage lines: LiDAR survey, flights at 30 m above the terrain, 8,996 panels checked one by one.

8 996 panels inspected
Thermography
1,262 medium-voltage line supports photographed in French Guiana: 128 km in 19 flying days
Mana, Sinnamary, Montsinéry-Tonnegrande, Saint-Georges — French Guiana2024

1,262 medium-voltage line supports photographed in French Guiana: 128 km in 19 flying days

Four medium-voltage feeders, from Mana to Saint-Georges: every support photographed using the operator’s method, 7,854 geotagged photos and a KML file of the lines.

1 262 supports
Structural inspection
Space Centre power network: 250 pylons inspected
Guiana Space Centre, Kourou2019–2023

Space Centre power network: 250 pylons inspected

In August 2019, inspection of 250 pylons of the base’s power network, so that our client could assess them and plan maintenance; the line supports were reviewed again until 2023.

250 pylons inspected in August 2019
Space centreStructural inspection
Urbasolar: five rooftop plants checked by thermography in Martinique and Guadeloupe
UrbasolarMartinique and Guadeloupe2024–2026

Urbasolar: five rooftop plants checked by thermography in Martinique and Guadeloupe

From March 2024 to April 2026: 4,082 modules in La Trinité, a string identification protocol, two roofs in Le Lamentin in a single morning, a campaign repeated in Jarry once the plant was producing, and a survey before rewiring.

5 rooftop plants surveyed
Thermography
Galisbay: 30.5 hectares by photogrammetry, then the ground by LiDAR for the earthworks
AlbiomaGalisbay, Saint-Martin2024–2026

Galisbay: 30.5 hectares by photogrammetry, then the ground by LiDAR for the earthworks

On a site next to Galisbay port, for an Albioma project: orthophoto and virtual tour in November 2024, LiDAR survey in March 2025, then in February 2026 the 15 cm ground points requested by the earthworks designer.

30,5 ha surveyed by photogrammetry in 2024
Surveying and LiDAR
Petit-Saut: ten versions of the construction virtual tour, then 44 panoramas for the inauguration
Voltalia, Triton GuyanePetit-Saut, Sinnamary, French Guiana2022–2026

Petit-Saut: ten versions of the construction virtual tour, then 44 panoramas for the inauguration

Throughout construction of the Petit-Saut biomass plant we rebuilt the site’s virtual tour after each photo campaign, up to the tenth version in August 2025. For the inauguration on 14 October 2025 we delivered a 44-panorama tour covering both the plant and the sawmill, together with the event video.

44 panoramas for the inauguration
Film, photo and 360°Construction monitoring
Thermal inspection of the Ariane 5 launch pad
With Arianespace and RMTGuiana Space Centre, Kourou2018–2019

Thermal inspection of the Ariane 5 launch pad

With Arianespace and RMT, thermal-camera check of the igniters of the launch pad’s hydrogen burn pond, from flight VA246 in December 2018.

VA246 first flight checked, 4 December 2018
Space centreThermography
Le Robert, Ducos, Rivière-Salée: three social housing estates surveyed in 3D
Ozanam and SMHLMLe Robert, Ducos, Rivière-Salée — Martinique2024–2025

Le Robert, Ducos, Rivière-Salée: three social housing estates surveyed in 3D

From May 2024 to July 2025, for two social landlords, we surveyed three housing estates by drone: colourised point clouds split building by building, plans and roof inspection photos, delivered to the architects and engineering firms in the formats their software reads.

7 ha Moulin à Vent estate, Le Robert
Surveying and LiDAR
Saint-Georges-de-l’Oyapock: 60 hectares of LiDAR to position a collimation mast
CNESSaint-Georges-de-l’Oyapock, French Guiana2021

Saint-Georges-de-l’Oyapock: 60 hectares of LiDAR to position a collimation mast

For CNES, a 2 km by 300 m corridor surveyed by LiDAR to study the lines of sight between a radar and a collimation mast 2.1 km away.

60 hectares, 2 km × 300 m
Space centreSurveying and LiDAR
The Enfant Perdu lighthouse, inspected from a boat
DGTM GuyaneL’Enfant Perdu, off Cayenne, and Île Royale2024–2025

The Enfant Perdu lighthouse, inspected from a boat

On 9 December 2025, for the Lighthouses and Beacons unit of DGTM, photographic coverage of the lighthouse and its islet, with the drone taking off from a boat that stayed offshore. In March 2024 we had photographed the Île Royale lighthouse for the same department.

2 lighthouses inspected for DGTM
Structural inspection
Crique Fouillée: 2.8 km of creek in 15 mm orthophoto to prepare dredging
CACLCrique Fouillée, island of Cayenne2026

Crique Fouillée: 2.8 km of creek in 15 mm orthophoto to prepare dredging

For the urban community’s stormwater service, a condition survey of an urban creek between Cayenne and Matoury: georeferenced orthophoto, mapping of debris jams and machine access points, video of the whole stretch.

2,8 km stretch
Surveying and LiDARFilm, photo and 360°
Approuague and Sinnamary forest: LiDAR and 3 cm orthophotos for the University of French Guiana
Université de GuyaneApprouague (Régina) and Sinnamary, French Guiana2025

Approuague and Sinnamary forest: LiDAR and 3 cm orthophotos for the University of French Guiana

For the Espace-Dev research unit, two forest plots surveyed by LiDAR and photography: 16 hectares on the Approuague in July 2025, with take-offs from a dugout canoe, then 48 hectares in Sinnamary in October.

16 ha on the Approuague, July 2025
Surveying and LiDAR
TDF sites in French Guiana: ten locations photographed at antenna height, from 18 to 60 m
TDFCayenne, Rémire-Montjoly, RN2, Sinnamary, Saint-Laurent-du-Maroni — French Guiana2023–2026

TDF sites in French Guiana: ten locations photographed at antenna height, from 18 to 60 m

Ten locations photographed at the antenna heights under study in 2023-2024, the capture of a site for its 3D model in 2025, 360° shots delivered the next day in 2026.

10 locations photographed in 2023-2024
Film, photo and 360°Surveying and LiDAR
Centre Littoral urban community: the bus rapid transit works, the arrival of the buses and two drinking-water structures
CACLIsland of Cayenne, Montsinéry-Tonnégrande, Roura2024–2026

Centre Littoral urban community: the bus rapid transit works, the arrival of the buses and two drinking-water structures

In April 2024, ten sectors of the bus rapid transit works; in January 2026, the unloading of the buses at the port of Dégrad-des-Cannes; in October 2026, the Montsinéry-Tonnégrande water tower and the Comté water intake.

10 sectors of the BRT works in 2024
Film, photo and 360°Construction monitoring
Balaté Nord: three drone visits to a housing district under construction
SEMSAMARBalaté Nord, Saint-Laurent-du-Maroni2025–2026

Balaté Nord: three drone visits to a housing district under construction

Aerial photos and videos of a housing scheme in Saint-Laurent-du-Maroni, from January 2025 to March 2026, with flight paths drawn by the client.

3 visits, January 2025 to March 2026
Construction monitoringFilm, photo and 360°
Quay no. 2 at Dégrad-des-Cannes: pile verticality from 4,410 photos
Grand Port Maritime de la GuyaneDégrad-des-Cannes, Rémire-Montjoly, French Guiana2023

Quay no. 2 at Dégrad-des-Cannes: pile verticality from 4,410 photos

Photogrammetry under the deck, at low tide and from a boat: 3D model of the quay, ortho-façade and tilt of the piles, delivered less than a month after the flights.

4 410 photos
Structural inspection
Saut Maman Valentin: seven survey campaigns on the banks downstream of the plant
VoltaliaSaut Maman Valentin, Mana, French Guiana2020–2025

Saut Maman Valentin: seven survey campaigns on the banks downstream of the plant

Since October 2020, drone LiDAR and photogrammetry downstream of the hydroelectric plant on the Mana: point clouds, 3 cm orthophotos and differential plans of the islet from one campaign to the next.

7 campaigns since October 2020
Surveying and LiDARFilm, photo and 360°
Coco Banane and Savane des Pères: two solar plants as virtual tours, 26 panoramas
VoltaliaMontsinéry-Tonnegrande and Sinnamary, French Guiana2025

Coco Banane and Savane des Pères: two solar plants as virtual tours, 26 panoramas

In November 2025 we produced virtual tours of two operating photovoltaic plants for Voltalia from two days of capture: 12 and 14 panoramas, tours online on 10 November, 2 cm per pixel orthophotos and source files handed over on the 18th.

26 panoramas across two plants
Film, photo and 360°Surveying and LiDAR
Pointe Combi: 66 hectares delivered in five days on Sentinel Cloud
FarmPointe Combi, Sinnamary2026

Pointe Combi: 66 hectares delivered in five days on Sentinel Cloud

Orthophoto and 7.2 cm surface model of a farm, with the footprint and cadastral parcels, available online.

66 hectares
Surveying and LiDAR
Four TDF antenna sites on the Oyapock, located and measured in 3D
TDFFrom Saint-Georges to Camopi, Oyapock, French Guiana2019

Four TDF antenna sites on the Oyapock, located and measured in 3D

In March 2019, drone photogrammetry of four sites between Saint-Georges and Camopi: 3D model, orthoplan, position and height of each antenna, delivered between 29 March and 4 April.

4 antenna sites
Surveying and LiDAR
Savane des Pères solar plant: from bare ground to commissioning
VoltaliaSavane des Pères, Sinnamary, French Guiana2019

Savane des Pères solar plant: from bare ground to commissioning

Reconnaissance, mapping before earthworks, then a time-lapse throughout the assembly of a 3.8 MW plant with battery storage.

3,8 MW of panels
Construction monitoringFilm, photo and 360°

Tell us about your project

Location, area or structure, expected deliverables and timing: with these details we can propose a method and a quote.

French Guiana3 rue Gramme
97310 Kourou
French Guiana
MartiniqueDomaine de Château Gaillard
Route des Trois-Îlets
97229 Les Trois-Îlets
Martinique
BrazilRua Santa Luzia, Centro
20030-041 Rio de Janeiro – RJ
Brazil