BHNS works at Balata: two time-lapse cameras for fourteen months
From 8 November 2024 to 31 December 2025, two time-lapse units and five days of aerial and ground filming on the RN2 upgrade in Matoury, for the civil works contractor.

Background
In Matoury, national road 2 is being rebuilt between the Balata junction and the PROGT roundabout to carry the bus rapid transit line: the project provides two traffic lanes and one bus lane in each direction, plus paths for pedestrians and cyclists. Ribal TP, which is carrying out the works for the DGTM, wanted regular images of the site for its communication, over works planned to last three years.
What we did
We installed two autonomous time-lapse units on fixed viewpoints over the site, the first on 8 November 2024 and the second on 16 December 2024, then handled their programming as the works progressed, their maintenance and the retrieval of the images. Five days of aerial and ground filming completed this continuous record: 16 July and 18 October 2024, 9 January, 27 March and 19 June 2025. A first edit covering the early months was delivered in 4K in June 2025, and a second one of about a minute and a half, tracing the works up to the June shoot, on 29 October 2025. The time-lapses were delivered by period, November 2024 to June 2025, July to September and October to December 2025, and as a fourteen-month cumulative version on 9 January 2026. The contract ended in late 2025, after which the units were removed.
In the mission log
Fourteen months of time-lapse on the Balata bus rapid transit works
Upgrade of the RN2 between Balata and the PROGT roundabout: five days of aerial and ground filming from July 2024 to June 2025, two time-lapse cameras from 8 November 2024 to 31 December 2025, two edits delivered in June and October 2025, cumulative time-lapse delivered on 9 January 2026.
- 14 months of time-lapse
- 2 cameras
- 5 filming days
Other projects

12,647 hectares of orthophotos at 3.5 cm for EPFA Guyane
From 4 December 2023 to 1 March 2024, eight sectors photographed at 3.5 cm per pixel, from Cayenne to Cacao: 343 flights, 184,464 photos, 50 ground control points and 26 check points. A second 6,545-hectare campaign began on 16 October 2026; its first sector was delivered on 19 October.

Corossony solar plant: 1,472 concrete footings surveyed at 2 mm per pixel before repowering
A 1:500 topographic plan of the plant in operation in September 2024, then the position and height of each of the 1,472 footings kept for the new structures, in December 2025.

Waste in western French Guiana: eight visits in Saint-Laurent, four Maroni villages at 1 cm
Since October 2024, photos taken from the same viewpoints at every visit to the Saint-Laurent-du-Maroni waste storage facility, with a 3 cm orthophoto and a plan since December 2024; in February 2026, the waste sites of four river villages surveyed at 1 cm.
Tell us about your project
Location, area or structure, expected deliverables and timing: with these details we can propose a method and a quote.