Genergies · Martinique, Guadeloupe and French Guiana · 2026

Eleven solar plants in 2026: 33,333 panels checked one by one

June to September 2026: eleven plants surveyed by thermography for Genergies in Martinique, Guadeloupe and French Guiana: 33,333 panels checked one by one.

Eleven solar plants in 2026: 33,333 panels checked one by one
The Le Carbet plant in the Sentinel Cloud thermography module
33 333panels checked in 2026
11plants in three territories
720–1 267W/m² of irradiance during the flights

Background

Genergies operates and maintains photovoltaic plants in the French Caribbean and French Guiana on behalf of their owners. On a solar plant, a panel that overheats, a string of modules that has been cut or tall grass casting shade means production lost every day. After a first plant in Le Carbet in June 2026, Genergies’ operations and maintenance department entrusted us in July with the Bellefontaine plant and eight ground-mounted plants in Guadeloupe, then in September with a rooftop installation in Matoury, each time with the same request: to know, panel by panel, what is not producing as expected and where to send the teams.

What we did

In Le Carbet on 17 June: 2,143 panels, report delivered the next day. In Bellefontaine, medium-voltage lines carried by 27 m pylons run above the plant: a LiDAR survey on 17 July provided the terrain model on which we set flights at 30 m on 20 July: 8,996 panels. In Guadeloupe, from 3 to 13 August, eight ground-mounted plants in Le Moule, Petit-Canal, Saint-François and Gourbeyre: 18,671 panels. In Matoury on 17 September, 3,523 panels on the roofs of three commercial buildings. Everywhere, visible flights (1 to 1.5 cm per pixel) and radiometric infrared flights (2.8 to 4 cm), under irradiance recorded between 720 and 1,267 W/m²; every report is checked by a second operator before being approved.

4 related missions in the log

  1. ThermographyFrench Guiana

    Thermal survey of a 1,152 kWp plant on three roofs in Matoury

    Matoury · Genergies

    Purchase order received on 10 September 2026, flights on the 17th over the roofs of three commercial buildings in the Larivot area: 3,523 panels checked; deliverables and Sentinel Cloud access on the 21st.

    • 3 523 panels
    • 3 roofs
    Read the article
  2. ThermographyGuadeloupe

    Diagnosis of eight ground-mounted photovoltaic plants in Guadeloupe

    Le Moule, Petit-Canal, Saint-François, Gourbeyre · Genergies

    Eight ground-mounted plants exporting all their output, flown from 3 to 5 August 2026 with additional flights on the 13th: 18,671 panels in infrared at 3 cm and visible at 1 cm, under 1,000 to 1,267 W/m²; a detailed report, a summary and a plan per plant, approved on 19 August.

    • 18 671 panels
    • 8 plants
    Read the article
  3. ThermographyMartinique

    Thermal survey of the Bellefontaine plant, beneath medium-voltage lines

    Bellefontaine · Genergies

    Medium-voltage lines on 27 m pylons above the plant: LiDAR survey on 17 July 2026 for the terrain model, then infrared and visible flights on 20 July, at 30 m above the terrain; 8,996 panels checked; results delivered and published on Sentinel Cloud on 30 July.

    • 8 996 panels
    • 30 m above the terrain
    Read the article
  4. ThermographyMartinique

    Thermal survey of the Le Carbet solar plant

    Le Carbet · Genergies

    On 17 June 2026, visible flights at 1.5 cm and infrared at 3 cm per pixel under 1,128 W/m²: 2,143 panels checked one by one; report delivered on 18 June.

    • 2 143 panels
    • 3 cm per pixel in infrared
    Read the article

All missions

Gallery

Tell us about your project

Location, area or structure, expected deliverables and timing: with these details we can propose a method and a quote.

French Guiana3 rue Gramme
97310 Kourou
French Guiana
MartiniqueDomaine de Château Gaillard
Route des Trois-Îlets
97229 Les Trois-Îlets
Martinique
BrazilRua Santa Luzia, Centro
20030-041 Rio de Janeiro – RJ
Brazil